Three working days after Friday, with Monday closed
2026-10-09 → 2026-10-15
The base date is excluded; counting starts on the next date in the chosen direction.
WORKDAYMAP / 01
Find a deadline. Work backwards. See every day that counts.
Apply an example, inspect the result, then save it if it is useful.
2026-10-09 → 2026-10-15
The base date is excluded; counting starts on the next date in the chosen direction.
2026-10-09 → 2026-10-14
The base date counts when eligible.
2026-10-13 → 2026-10-09
The base date is excluded; counting starts on the next date in the chosen direction.
Your target date
Zero days returns the base date, even if it is a day off.
Temporary browser storage is unavailable. Restore before reloading or changing language; the exact undo state may otherwise be lost.
Save up to 5 scenarios in this browser. They do not sync to an account or cloud. Remove them from this library.
No saved scenarios yet.
WORKDAYMAP / 02
Choose a direction, a base date and a number of working days. The calculator visits each calendar date in that direction. Weekly days off and extra closures are skipped; exceptional working days override weekly days off. A date cannot be both an extra closure and an exceptional working day. For backward calculations, the same rules are applied in reverse: this gives a date offset, not a guarantee of available project capacity. A zero-day calculation returns the base date. The calendar shows exactly which dates were counted. Results are planning aids, not statutory or contractual deadline advice. Confirm the actual calendar with the people involved.
Try a Friday start with a Monday closure, then compare including the start date. The guide explains each counted and skipped day.
Start on 9 October 2026, exclude the base date, leave Saturday and Sunday off, and enter 12 October as a closure. Tuesday 13 is day 1, Wednesday 14 is day 2 and Thursday 15 is day 3. The closure is an example you enter yourself, not an automatically detected public holiday.
Your target date 2026-10-15
Use the same inputs as the first example, but turn on "Count the base date if it is a working day". Friday 9 October is a working day, so it becomes day 1. Saturday, Sunday and the Monday closure are skipped, Tuesday 13 is day 2 and Wednesday 14 is day 3. Counting the base date moves the result one working day earlier, from Thursday 15 to Wednesday 14.
Your target date 2026-10-14
Start from Tuesday 13 October and count 2 working days back, without counting the base date. Monday 12 is entered as a closure. Saturday 10 is normally a weekly day off, but here it is entered as an exceptional working day, so it counts as day 1. Sunday 11 is still skipped, and Friday 9 is day 2. Without the exceptional Saturday, the result would be one working day earlier: Thursday 8 October.
Your calculated start date 2026-10-09
YYYY-MM-DD per line (commas also work). Public holidays are not filled in for you.No. Teams close on different days, and the language menu does not pick a country. Add the holidays and closures that apply to you under "Extra days off".
Not by default. Turn on "Count the base date if it is a working day" to make it day 1. If the base date is a day off under your rules, it is skipped either way.
It turns a date that would otherwise be a weekly day off into a working day, such as a Saturday make-up day. A date can't be both an extra day off and an exceptional working day.
The result is the base date itself, even if that date is a day off.
No. At least one weekday must remain a working day.
Dates from 1900-01-01 to 2100-12-31 and 0 to 1000 business days. Whole dates only: no times of day, time zones or half-days.
The base date, direction, number of days, the base-date setting, weekly days off, extra days off and exceptional working days, all in the URL. Anyone with the link can see them, so don't share confidential schedules.
No. It is a planning aid. Legal and contractual deadlines follow their own rules; confirm them with the people or the rules involved.
More detail: How counting works, Weekend Days in the UAE, Saudi Arabia and Israel: How Business Days Are Counted, Public Holidays That Move: Lunar New Year, Eid and Easter in Business-Day Math (2026–2027 dates), Business Days in 2027: US Working Days by Month, NETWORKDAYS vs WORKDAY in Excel and UK Working Days in 2027.