Weekend Days in the UAE, Saudi Arabia and Israel: How Business Days Are Counted
A common shortcut says that business days in the Middle East run from Sunday to Thursday. For the three countries on this page, that is only partly true, and the difference changes the date you get when you count working days. Saudi Arabia’s official weekend is Friday and Saturday. The UAE federal government moved to a Saturday–Sunday weekend in 2022. In Israel, the law guarantees a weekly rest that includes the Sabbath, and the civil service mostly works Sunday to Thursday. This page summarises what the official sources say, as checked on 30 October 2026, and shows how to enter each pattern in WorkdayMap and in Excel. It is a planning aid, not legal advice: employers, contracts and sectors can set different schedules.
Why this page is not titled “Friday–Saturday weekends”
This article was planned under the title “How business days are counted in the UAE, Saudi Arabia and Israel (Friday–Saturday weekends)”. While checking sources, that premise did not hold for the UAE: the federal government weekend has been Saturday and Sunday, with a half-day on Friday, since 1 January 2022. Grouping the three countries under one weekend would give a wrong count for anyone following the UAE federal calendar, so the page covers each country separately instead.
United Arab Emirates: Saturday–Sunday for the federal government
According to the UAE Government Portal, federal government working hours are Monday to Thursday from 7:30 a.m. to 3:30 p.m. and Friday from 7:30 a.m. to 12:00 noon. FAHR Circular No. 18 of 2021 set that schedule from 1 January 2022, describing the weekend as Saturday, Sunday and half of Friday. The change was announced by the Emirates News Agency (WAM) in December 2021.
The private sector is not tied to that schedule. The Portal’s page on private-sector leave says employees are entitled to at least one day of paid rest per week “as specified in the employment contract or the company’s work regulations”, and that companies may grant additional rest days. A UAE supplier’s weekend is therefore something to confirm, not assume.
Holidays add a second layer. The Portal’s public holidays page explains that Islamic holidays depend on moon sighting, and that under Article 3 of Cabinet Resolution No. 27 of 2024 a holiday that falls on a weekend or coincides with another holiday is not moved to another day. In practice the dates are announced close to the event: for Eid Al Fitr 2026, WAM reported on 23 February 2026 that the private-sector holiday would run from Thursday 19 March to Saturday 21 March, extended to Sunday 22 March if Ramadan completed 30 days.
One more practical point: WorkdayMap counts whole dates and does not model half-days. For a UAE federal calendar, decide up front whether the short Friday counts as a working day for your purpose, for example whether a document received on Friday morning is treated as received that day.
Saudi Arabia: Friday–Saturday by royal order
Royal Order No. A/185, dated 14/8/1434H and published by the Saudi Press Agency on 23 June 2013, set official working days from Sunday to Thursday, with Friday and Saturday as the weekly holiday. It applied to ministries, government bodies, financial institutions, the central bank and the capital-market authorities from 29 June 2013, and to schools and universities from the following academic year.
The Implementing Regulation for Human Resources in the Civil Service repeats this: Article 10 lists Sunday to Thursday as official working days, and Article 127 lists Friday and Saturday as the weekend. Article 127 also contains a rule worth coding carefully. National Day is 23 September; if it falls on a Saturday, the following Sunday is a holiday, and if it falls on a Friday, the preceding Thursday is a holiday. Article 128 adds that a single working day between two official holidays is itself a holiday. The same article sets long Eid periods for government employees: Eid al-Fitr from 25 Ramadan to the end of 5 Shawwal, and Eid al-Adha from 5 to 15 Dhul-Hijjah.
Private employers follow the Labor Law instead. Article 104, available through WIPO Lex, makes Friday the weekly rest day and lets an employer substitute another day after notifying the labour office. The law fixes one rest day; whether a private company also closes on Saturday depends on the employer.
Israel: Sabbath rest and a Sunday–Thursday civil-service week
Israel’s Hours of Work and Rest Law, 5711-1951, sets the rule in terms of rest rather than weekend days. Section 7, as quoted in paragraph 31.211 of the civil-service rules (Hebrew excerpt published by the National Insurance Institute), requires a weekly rest of at least 36 consecutive hours; for Jewish workers it includes the Sabbath, and for non-Jewish workers it is the Sabbath, Sunday or Friday according to their custom. The same paragraph states that Saturday is a day of rest in all government offices, except units that operate every day of the week.
For government offices, the civil-service rules (Takshir) in that excerpt are more specific. Paragraph 31.111 says that in offices with a five-day week, the working week is Sunday to Thursday, from 07:30 to 16:00 Sunday to Wednesday and until 15:30 on Thursday; offices with essential Friday activity work 07:30–14:00 that day. Offices with a six-day week work Sunday to Friday. The same paragraph gives Muslim and Druze employees, whose rest day is Friday, a Sunday–Thursday week with Saturday free, and Christian employees, whose rest day is Sunday, a Monday–Friday week.
So a Friday–Saturday weekend is a reasonable default for many Israeli offices, but it is not one national rule. A Sunday–Friday office, or a team that rests on Saturday and Sunday, will produce a different result.
Setting the weekend in WorkdayMap
- Open the calculator and choose “Add business days” or “Work back from a deadline”.
- Under “Your working calendar”, set “Weekly days off”. For a Friday–Saturday calendar, select Friday and Saturday and clear Sunday. For the UAE federal calendar, keep Saturday and Sunday.
- Add announced public holidays under “Extra days off”, one date per line. WorkdayMap does not load a holiday calendar, so Eid dates in particular need to be entered once they are announced.
The two examples below use the same inputs except the weekend. Starting on Wednesday 4 November 2026 and adding two business days, the result differs by two calendar days.
Two business days after Wednesday, Friday–Saturday weekend
Thursday 5 November is day 1. Friday and Saturday are skipped, so Sunday 8 November is day 2. This matches a Saudi government calendar or a five-day Israeli office.
- Add business days
- 2026-11-04
- Business days
- 2
- Count the base date if it is a working day
- No
- Weekly days off
- Friday · Saturday
- Extra days off
- None
- Exceptional working days
- None
Your target date 2026-11-08
- 2026-11-04 — Base date, not counted
- 2026-11-05 — Working day · Working days counted: 1
- 2026-11-06 — Weekly day off
- 2026-11-07 — Weekly day off
- 2026-11-08 — Working day · Working days counted: 2
The same count with a Saturday–Sunday weekend
Thursday 5 November is day 1 and Friday 6 November is day 2. This matches the UAE federal week, treating the short Friday as a working day.
- Add business days
- 2026-11-04
- Business days
- 2
- Count the base date if it is a working day
- No
- Weekly days off
- Saturday · Sunday
- Extra days off
- None
- Exceptional working days
- None
Your target date 2026-11-06
- 2026-11-04 — Base date, not counted
- 2026-11-05 — Working day · Working days counted: 1
- 2026-11-06 — Working day · Working days counted: 2
The same weekends in Excel: NETWORKDAYS.INTL
Excel’s NETWORKDAYS.INTL takes a weekend argument. Code 1 (or omitted) means Saturday and Sunday, code 7 means Friday and Saturday, and codes 11 to 17 mean a single day off, with 16 for Friday only. You can also pass a seven-character string that starts on Monday, where 1 marks a non-working day: Friday–Saturday is "0000110". Microsoft’s own example uses code 7 to count 22 working days between 1 January and 1 February 2006 after removing four Fridays, four Saturdays and two holidays.
- Friday–Saturday:
=NETWORKDAYS.INTL(DATE(2026,11,1),DATE(2026,11,30),7)counts 22 working days in November 2026. - Saturday–Sunday: the same range with code
1counts 21. - Friday only, the Labor Law minimum in Saudi Arabia: code
16counts 26.
These counts come from listing the 30 days of November 2026, which begins on a Sunday. Note that NETWORKDAYS.INTL includes both the start and end dates when they are working days. That answers “how many working days are in this range”, which is a different question from “which date is N business days after this one”, the question WorkdayMap answers. Add announced holidays as the fourth argument.
A short checklist before you share a date
- Which calendar applies: government, a specific private employer, or a bank?
- Which weekly days off does that calendar use, and is there a half-day?
- Have this year’s Islamic holidays been officially announced yet, or are you using an estimate?
- Does the base date count? Say so alongside the result so others can reproduce it.
For holidays that move from year to year, including Eid, see Public Holidays That Move: Lunar New Year, Eid and Easter in Business-Day Math. For the counting rules themselves, see How counting works.
Sources (checked 30 October 2026)
- UAE Government Portal: Working hours in the public sector
- FAHR Circular No. 18 of 2021 (PDF)
- WAM, 7 December 2021: UAE government announces four-and-a-half-day working week
- UAE Government Portal: Types of leaves (private sector)
- UAE Government Portal: Public holidays
- WAM, 23 February 2026: Eid Al Fitr holiday announced for private sector
- Saudi Press Agency, 23 June 2013: Royal Order A/185 (Arabic)
- Saudi Arabia: Implementing Regulation for Human Resources in the Civil Service (PDF)
- WIPO Lex: Saudi Arabia Labor Law
- National Insurance Institute of Israel: civil-service rules, chapter 31 excerpt (Hebrew, PDF)
- Microsoft Support: NETWORKDAYS.INTL function